Trump might use Greenland for 10,000 EH/s Bitcoin mining hub from stranded vitality if it turns into part of the US

Coininsight by Coininsight
January 9, 2026
in Crypto Mining
0
Trump might use Greenland for 10,000 EH/s Bitcoin mining hub from stranded vitality if it turns into part of the US
189
SHARES
1.5k
VIEWS
Share on FacebookShare on Twitter


Speak of the US shopping for Greenland has returned to Washington, and miners are monitoring the facility tasks on the island.

The White Home stated a U.S. buy of Greenland is an “lively dialogue,” in line with Reuters.

For Bitcoin miners, the extra actionable clock is Greenland’s industrial energy planning.

How Greenland’s hydropower interprets into actual Bitcoin mining capability

Greenland’s authorities stated it plans to open a public tender spherical within the second half of 2026 for the 2 largest mapped hydropower websites supposed for industrial use, Tasersiaq (web site 07.e) and Tarsartuup Tasersua (web site 06.g), in line with Naalakkersuisut.gl.

It stated the 2 websites collectively might produce greater than 9,500 gigawatt-hours yearly.

Mining math is simple.

Bitmain’s Antminer S21 specification lists 200 TH/s at 3,500 watts, or about 17.5 joules per terahash, in line with Bitmain.

Utilizing a planning energy utilization effectiveness worth close to 1.1 (cooling and overhead), 1 megawatt of facility energy equates to about 0.052 exahash per second (EH/s) at 17.5 J/TH.

That suggests about 0.041–0.061 EH/s throughout a 15–22 J/TH effectivity band.

Facility energy (MW)Hashrate ceiling (EH/s) @ 17.5 J/TH, PUE 1.1
50.26
251.30
502.60
1005.19

Greenland’s put in base is much smaller than the tendered ambition.

Nukissiorfiit reviews about 91.3 megawatts of hydropower capability throughout its techniques and a mean electrical energy gross sales worth of about DKK 1.81 per kilowatt-hour in 2024, in line with its annual report.

Retail-style pricing at that degree doesn’t map cleanly onto mining economics.

That’s the reason any massive construct will depend on industrial energy buy agreements or behind-the-meter provide at new technology, relatively than shopping for energy like a standard buyer.

The shortage of a nationwide grid narrows the paths to scale.

Energy stations usually serve cities and settlements as native techniques, with restricted interconnection, in line with Entice Greenland.

That pushes early “stranded” or surplus-energy ideas towards colocating versatile load at particular vegetation.

Greenland reporting has mentioned using surplus vitality within the context of reducing vitality prices, in line with Greenland Assessment.

If 5–25 megawatts may be aggregated behind the meter close to current technology, the ceiling is about 0.21–1.52 EH/s throughout the 15–22 J/TH band (about 0.26–1.30 EH/s at 17.5 J/TH).

That’s sufficient for pilots, however not sufficient to maneuver international community share.

The subsequent rung up is Nuuk’s principal hydro plant.

Scaling bitcoin mining in Greenland: from surplus energy pilots to grid-level enlargement

Buksefjord is deliberate to develop from 45 megawatts to 121 megawatts, with building anticipated to start in 2026 and commissioning focused for 2032, in line with NunaGreen.

The European Funding Financial institution’s undertaking pipeline references a roughly 76-megawatt Buksefjord-3 construct close to the prevailing 45-megawatt plant.

If 50–121 megawatts of output had been contracted to miners, {the electrical} ceiling is about 2.07–7.33 EH/s throughout the 15–22 J/TH band (about 2.6–6.3 EH/s at 17.5 J/TH).

That assumes these megawatts should not absorbed by Nuuk demand development and electrification plans.

The 2-site tender is the place Greenland turns into a gigawatt-scale dialogue.

Greater than 9,500 GWh a 12 months equates to about 1.08 gigawatts of common energy if absolutely utilized.

That suggests an electricity-limited hashrate ceiling round 44.8–65.7 EH/s throughout the 15–22 J/TH band (about 56.0 EH/s at 17.5 J/TH).

Monitoring websites place Bitcoin hashrate round 1.03–1.17 zetahash per second (ZH/s), and minerstat locations issue close to 148 trillion, in line with minerstat.

On that baseline, a totally utilized 1.08 GW mine implies about 4–6% of at this time’s community hashrate, with the share shrinking if international hashrate expands.

May Trump-linked capital eye Greenland’s vitality surplus for Bitcoin mining enlargement?

Trump-linked mining capital is already forming, which is why Greenland’s energy calendar might draw consideration contained in the sector.

BC Game
BC Game

Hut 8 partnered with Eric Trump to launch American Bitcoin, combining Hut 8’s mining operations with an investor group that features Donald Trump Jr., whereas Hut 8 retained an 80% stake.

American Bitcoin stated put in hashrate expanded to about 24 EH/s and cited fleet effectivity round 16.4 J/TH as of Sept. 1, 2025, in line with the corporate.

American Bitcoin plunged 50% during a crypto rally, exposing a fatal flaw in the “Trump proxy” tradeAmerican Bitcoin plunged 50% during a crypto rally, exposing a fatal flaw in the “Trump proxy” trade
Associated Studying

American Bitcoin plunged 50% throughout a crypto rally, exposing a deadly flaw within the “Trump proxy” commerce

BTC sits above $93,000, however Trump-linked miner ABTC plunged on a share unlock. Right here’s the mechanics behind the divergence.

Dec 4, 2025 · Gino Matos

Utilizing the identical PUE 1.1 planning worth, 24 EH/s implies roughly 430 megawatts of facility energy at 16.4 J/TH (about 460 megawatts at 17.5 J/TH).

Which means a totally utilized 1.08 GW tender buildout might energy an American Bitcoin-sized fleet greater than as soon as over, if the offtake had been devoted to mining and if transmission and building timelines cleared.

Even in a “what if” sovereignty state of affairs, the constraints keep sensible.

Industrial hydro requires multiyear building, heavy logistics, and long-duration offtake, and mines want resilient knowledge hyperlinks, spares, and import capability for ASIC fleets.

Greenland Join hyperlinks Canada, Nuuk, Qaqortoq, and Iceland by subsea cable, in line with Tusass, however it doesn’t remedy transmission to distant hydro basins.

Clear, agency megawatts additionally face competitors from different masses.

The Worldwide Vitality Company has warned that AI will drive greater electrical energy demand from knowledge facilities, which might increase the chance price of dedicating long-duration renewable output to mining.

Diplomacy will form financing circumstances round any “Trump Greenland mine” thesis.

European officers have harassed that Greenland’s standing rests on consent and sovereignty norms, in line with Reuters.

Greenland’s tender spherical deliberate for the second half of 2026 will set the baseline for any large-scale Bitcoin mining offtake from new hydropower on the island.

Why Greenland’s vitality economics and geopolitics matter for large-scale Bitcoin mining

Nevertheless, if Greenland had been introduced beneath U.S. jurisdiction and handled as an vitality buildout zone relatively than a small, fragmented utility market, the renewable ceiling that issues for mining would shift from 1-GW-class hydro tenders to additionally give attention to wind.

In line with a techniques research revealed in Vitality and listed on ScienceDirect, Greenland’s onshore wind technical potential is about 333 GW nameplate, producing about 1,487 TWh per 12 months beneath the belief that 20% of Greenland’s ice-free space is obtainable.

That equates to about 170 GW of common technology on an vitality foundation.

Output can be variable and would require transmission, overbuild, curtailment, storage, and firming to serve a 24/7 load at scale.

Translating that energy-only ceiling into hashrate exhibits how far the “Trump Greenland mine” narrative may be pushed in concept.

At 15–22 J/TH with PUE round 1.1, 170 GW of common technology implies roughly 7.0–10.4 ZH/s of hashing capability if miners might take in the common output as a versatile load, nicely above at this time’s community.

Present hashrate stands at round 1 ZH/s, so buying sufficient mining machines to facilitate such a build-out makes this largely a theoretical train in potential forward-facing limits.

Additionally, 10 ZH/s shouldn’t be a “24/7 agency baseload” except you add huge transmission, overbuild, curtailment, and storage/firming (or settle for downtime/variable operation). It’s a ceiling based mostly on absorbing common wind vitality relatively than delivering assured energy each hour.

Nonetheless, a crude linear extrapolation of that very same research’s land-availability assumption from 20% to 100% implies about 7,435 TWh per 12 months (about 848 GW common), or roughly 34.8–51.7 ZH/s.

That could be a physics-and-maps ceiling relatively than a construct plan, given siting, allowing, ports, roads, and HVDC necessities.

In line with IRENA, the worldwide common put in price for brand spanking new onshore wind in 2023 was about $1,154 per kW.

That places 333 GW at roughly $384 billion in generators alone earlier than Arctic premiums, transmission, and firming infrastructure.

OneMiners lists an Antminer S21 XP Hyd at 473 TH/s for $6,799. To make the most of 333 GW, you’d want roughly 21,141,650 miners, which involves round $143 billion.

Nevertheless, that’s simply the ASIC buy price. It excludes delivery, duties/VAT, spares, racks/PSUs/networking, buildings, cooling/hydro loops, and commissioning, stuff that’s very non-trivial at tens of hundreds of thousands of models.

All in, assuming {hardware} is obtainable (which it is not), an funding of round $427 billion would give a miner based mostly in Greenland sufficient renewable energy-sourced hash energy to regulate the $1.8 trillion Bitcoin community ten occasions over. Or round $55 billion to equal the present community hashrate (it isn’t merely 1/tenth on account of scaling).

These are all “again of an envelope” figures with plenty of caveats and assumptions, however the actuality is that there is sufficient unused vitality in Greenland to energy the Bitcoin community many occasions over. With Starlink deployment, you possibly can most likely construct some main AI datacenters, too.

Talked about on this article

Related articles

This Analyst Is Dumping Bitcoin Over Quantum Computing Fears

This Analyst Is Dumping Bitcoin Over Quantum Computing Fears

January 16, 2026
Belgium’s Second-Largest Financial institution Launches Crypto Buying and selling

Belgium’s Second-Largest Financial institution Launches Crypto Buying and selling

January 16, 2026


Speak of the US shopping for Greenland has returned to Washington, and miners are monitoring the facility tasks on the island.

The White Home stated a U.S. buy of Greenland is an “lively dialogue,” in line with Reuters.

For Bitcoin miners, the extra actionable clock is Greenland’s industrial energy planning.

How Greenland’s hydropower interprets into actual Bitcoin mining capability

Greenland’s authorities stated it plans to open a public tender spherical within the second half of 2026 for the 2 largest mapped hydropower websites supposed for industrial use, Tasersiaq (web site 07.e) and Tarsartuup Tasersua (web site 06.g), in line with Naalakkersuisut.gl.

It stated the 2 websites collectively might produce greater than 9,500 gigawatt-hours yearly.

Mining math is simple.

Bitmain’s Antminer S21 specification lists 200 TH/s at 3,500 watts, or about 17.5 joules per terahash, in line with Bitmain.

Utilizing a planning energy utilization effectiveness worth close to 1.1 (cooling and overhead), 1 megawatt of facility energy equates to about 0.052 exahash per second (EH/s) at 17.5 J/TH.

That suggests about 0.041–0.061 EH/s throughout a 15–22 J/TH effectivity band.

Facility energy (MW)Hashrate ceiling (EH/s) @ 17.5 J/TH, PUE 1.1
50.26
251.30
502.60
1005.19

Greenland’s put in base is much smaller than the tendered ambition.

Nukissiorfiit reviews about 91.3 megawatts of hydropower capability throughout its techniques and a mean electrical energy gross sales worth of about DKK 1.81 per kilowatt-hour in 2024, in line with its annual report.

Retail-style pricing at that degree doesn’t map cleanly onto mining economics.

That’s the reason any massive construct will depend on industrial energy buy agreements or behind-the-meter provide at new technology, relatively than shopping for energy like a standard buyer.

The shortage of a nationwide grid narrows the paths to scale.

Energy stations usually serve cities and settlements as native techniques, with restricted interconnection, in line with Entice Greenland.

That pushes early “stranded” or surplus-energy ideas towards colocating versatile load at particular vegetation.

Greenland reporting has mentioned using surplus vitality within the context of reducing vitality prices, in line with Greenland Assessment.

If 5–25 megawatts may be aggregated behind the meter close to current technology, the ceiling is about 0.21–1.52 EH/s throughout the 15–22 J/TH band (about 0.26–1.30 EH/s at 17.5 J/TH).

That’s sufficient for pilots, however not sufficient to maneuver international community share.

The subsequent rung up is Nuuk’s principal hydro plant.

Scaling bitcoin mining in Greenland: from surplus energy pilots to grid-level enlargement

Buksefjord is deliberate to develop from 45 megawatts to 121 megawatts, with building anticipated to start in 2026 and commissioning focused for 2032, in line with NunaGreen.

The European Funding Financial institution’s undertaking pipeline references a roughly 76-megawatt Buksefjord-3 construct close to the prevailing 45-megawatt plant.

If 50–121 megawatts of output had been contracted to miners, {the electrical} ceiling is about 2.07–7.33 EH/s throughout the 15–22 J/TH band (about 2.6–6.3 EH/s at 17.5 J/TH).

That assumes these megawatts should not absorbed by Nuuk demand development and electrification plans.

The 2-site tender is the place Greenland turns into a gigawatt-scale dialogue.

Greater than 9,500 GWh a 12 months equates to about 1.08 gigawatts of common energy if absolutely utilized.

That suggests an electricity-limited hashrate ceiling round 44.8–65.7 EH/s throughout the 15–22 J/TH band (about 56.0 EH/s at 17.5 J/TH).

Monitoring websites place Bitcoin hashrate round 1.03–1.17 zetahash per second (ZH/s), and minerstat locations issue close to 148 trillion, in line with minerstat.

On that baseline, a totally utilized 1.08 GW mine implies about 4–6% of at this time’s community hashrate, with the share shrinking if international hashrate expands.

May Trump-linked capital eye Greenland’s vitality surplus for Bitcoin mining enlargement?

Trump-linked mining capital is already forming, which is why Greenland’s energy calendar might draw consideration contained in the sector.

BC GameBC Game

Hut 8 partnered with Eric Trump to launch American Bitcoin, combining Hut 8’s mining operations with an investor group that features Donald Trump Jr., whereas Hut 8 retained an 80% stake.

American Bitcoin stated put in hashrate expanded to about 24 EH/s and cited fleet effectivity round 16.4 J/TH as of Sept. 1, 2025, in line with the corporate.

American Bitcoin plunged 50% during a crypto rally, exposing a fatal flaw in the “Trump proxy” tradeAmerican Bitcoin plunged 50% during a crypto rally, exposing a fatal flaw in the “Trump proxy” trade
Associated Studying

American Bitcoin plunged 50% throughout a crypto rally, exposing a deadly flaw within the “Trump proxy” commerce

BTC sits above $93,000, however Trump-linked miner ABTC plunged on a share unlock. Right here’s the mechanics behind the divergence.

Dec 4, 2025 · Gino Matos

Utilizing the identical PUE 1.1 planning worth, 24 EH/s implies roughly 430 megawatts of facility energy at 16.4 J/TH (about 460 megawatts at 17.5 J/TH).

Which means a totally utilized 1.08 GW tender buildout might energy an American Bitcoin-sized fleet greater than as soon as over, if the offtake had been devoted to mining and if transmission and building timelines cleared.

Even in a “what if” sovereignty state of affairs, the constraints keep sensible.

Industrial hydro requires multiyear building, heavy logistics, and long-duration offtake, and mines want resilient knowledge hyperlinks, spares, and import capability for ASIC fleets.

Greenland Join hyperlinks Canada, Nuuk, Qaqortoq, and Iceland by subsea cable, in line with Tusass, however it doesn’t remedy transmission to distant hydro basins.

Clear, agency megawatts additionally face competitors from different masses.

The Worldwide Vitality Company has warned that AI will drive greater electrical energy demand from knowledge facilities, which might increase the chance price of dedicating long-duration renewable output to mining.

Diplomacy will form financing circumstances round any “Trump Greenland mine” thesis.

European officers have harassed that Greenland’s standing rests on consent and sovereignty norms, in line with Reuters.

Greenland’s tender spherical deliberate for the second half of 2026 will set the baseline for any large-scale Bitcoin mining offtake from new hydropower on the island.

Why Greenland’s vitality economics and geopolitics matter for large-scale Bitcoin mining

Nevertheless, if Greenland had been introduced beneath U.S. jurisdiction and handled as an vitality buildout zone relatively than a small, fragmented utility market, the renewable ceiling that issues for mining would shift from 1-GW-class hydro tenders to additionally give attention to wind.

In line with a techniques research revealed in Vitality and listed on ScienceDirect, Greenland’s onshore wind technical potential is about 333 GW nameplate, producing about 1,487 TWh per 12 months beneath the belief that 20% of Greenland’s ice-free space is obtainable.

That equates to about 170 GW of common technology on an vitality foundation.

Output can be variable and would require transmission, overbuild, curtailment, storage, and firming to serve a 24/7 load at scale.

Translating that energy-only ceiling into hashrate exhibits how far the “Trump Greenland mine” narrative may be pushed in concept.

At 15–22 J/TH with PUE round 1.1, 170 GW of common technology implies roughly 7.0–10.4 ZH/s of hashing capability if miners might take in the common output as a versatile load, nicely above at this time’s community.

Present hashrate stands at round 1 ZH/s, so buying sufficient mining machines to facilitate such a build-out makes this largely a theoretical train in potential forward-facing limits.

Additionally, 10 ZH/s shouldn’t be a “24/7 agency baseload” except you add huge transmission, overbuild, curtailment, and storage/firming (or settle for downtime/variable operation). It’s a ceiling based mostly on absorbing common wind vitality relatively than delivering assured energy each hour.

Nonetheless, a crude linear extrapolation of that very same research’s land-availability assumption from 20% to 100% implies about 7,435 TWh per 12 months (about 848 GW common), or roughly 34.8–51.7 ZH/s.

That could be a physics-and-maps ceiling relatively than a construct plan, given siting, allowing, ports, roads, and HVDC necessities.

In line with IRENA, the worldwide common put in price for brand spanking new onshore wind in 2023 was about $1,154 per kW.

That places 333 GW at roughly $384 billion in generators alone earlier than Arctic premiums, transmission, and firming infrastructure.

OneMiners lists an Antminer S21 XP Hyd at 473 TH/s for $6,799. To make the most of 333 GW, you’d want roughly 21,141,650 miners, which involves round $143 billion.

Nevertheless, that’s simply the ASIC buy price. It excludes delivery, duties/VAT, spares, racks/PSUs/networking, buildings, cooling/hydro loops, and commissioning, stuff that’s very non-trivial at tens of hundreds of thousands of models.

All in, assuming {hardware} is obtainable (which it is not), an funding of round $427 billion would give a miner based mostly in Greenland sufficient renewable energy-sourced hash energy to regulate the $1.8 trillion Bitcoin community ten occasions over. Or round $55 billion to equal the present community hashrate (it isn’t merely 1/tenth on account of scaling).

These are all “again of an envelope” figures with plenty of caveats and assumptions, however the actuality is that there is sufficient unused vitality in Greenland to energy the Bitcoin community many occasions over. With Starlink deployment, you possibly can most likely construct some main AI datacenters, too.

Talked about on this article
Tags: BitcoinEHsEnergyGreenlandHubMiningPartstrandedTRUMP
Share76Tweet47

Related Posts

This Analyst Is Dumping Bitcoin Over Quantum Computing Fears

This Analyst Is Dumping Bitcoin Over Quantum Computing Fears

by Coininsight
January 16, 2026
0

Christopher Wooden, world head of fairness technique at Jefferies, has eradicated Bitcoin from his flagship Greed & Worry mannequin portfolio,...

Belgium’s Second-Largest Financial institution Launches Crypto Buying and selling

Belgium’s Second-Largest Financial institution Launches Crypto Buying and selling

by Coininsight
January 16, 2026
0

AltcoinsBitcoin Belgium’s conservative banking panorama is about to alter as KBC Group prepares to introduce cryptocurrency buying and selling for...

How solo Bitcoin miners received 22 blocks in 12 months as one other hit the jackpot this week

How solo Bitcoin miners received 22 blocks in 12 months as one other hit the jackpot this week

by Coininsight
January 14, 2026
0

A single Bitcoin (BTC) miner collected a full block reward on Jan. 13, claiming 3.125 BTC plus charges value near...

Bitcoin Worth Rockets Previous $96K As Technique ($MSTR) Jumps 8%

Bitcoin Worth Rockets Previous $96K As Technique ($MSTR) Jumps 8%

by Coininsight
January 14, 2026
0

The Bitcoin worth surged via the $96,000 stage this afternoon, pushing decisively above a key resistance zone and signaling a...

Why Europe’s Digital Euro Is Turning into a Strategic Necessity

Why Europe’s Digital Euro Is Turning into a Strategic Necessity

by Coininsight
January 13, 2026
0

Fintech A gaggle of outstanding economists is urging Europe to rethink the way it treats cash in a digital world...

Load More
  • Trending
  • Comments
  • Latest
MetaMask Launches An NFT Reward Program – Right here’s Extra Data..

MetaMask Launches An NFT Reward Program – Right here’s Extra Data..

July 24, 2025
Haedal token airdrop information

Haedal token airdrop information

April 24, 2025
BitHub 77-Bit token airdrop information

BitHub 77-Bit token airdrop information

February 6, 2025
MilkyWay ($milkTIA, $MILK) Token Airdrop Information

MilkyWay ($milkTIA, $MILK) Token Airdrop Information

March 4, 2025
Kuwait bans Bitcoin mining over power issues and authorized violations

Kuwait bans Bitcoin mining over power issues and authorized violations

2
The Ethereum Basis’s Imaginative and prescient | Ethereum Basis Weblog

The Ethereum Basis’s Imaginative and prescient | Ethereum Basis Weblog

2
Unchained Launches Multi-Million Greenback Bitcoin Legacy Mission

Unchained Launches Multi-Million Greenback Bitcoin Legacy Mission

1
Earnings Preview: Microsoft anticipated to report larger Q3 income, revenue

Earnings Preview: Microsoft anticipated to report larger Q3 income, revenue

1
White Home Might Drop Crypto Invoice After Coinbase Withdrawal: Report

White Home Might Drop Crypto Invoice After Coinbase Withdrawal: Report

January 17, 2026
Jefferies’ Drops Bitcoin Over Quantum Computing Menace

Jefferies’ Drops Bitcoin Over Quantum Computing Menace

January 17, 2026
Professional insights on constructing a risk-aligned compliance roadmap for 2026

Professional insights on constructing a risk-aligned compliance roadmap for 2026

January 17, 2026
Bitcoin Logs Third Weekly Achieve as ETF Cash Quietly Flows In

Bitcoin Logs Third Weekly Achieve as ETF Cash Quietly Flows In

January 17, 2026

CoinInight

Welcome to CoinInsight.co.uk – your trusted source for all things cryptocurrency! We are passionate about educating and informing our audience on the rapidly evolving world of digital assets, blockchain technology, and the future of finance.

Categories

  • Bitcoin
  • Blockchain
  • Crypto Mining
  • Ethereum
  • Future of Crypto
  • Market
  • Regulation
  • Ripple

Recent News

White Home Might Drop Crypto Invoice After Coinbase Withdrawal: Report

White Home Might Drop Crypto Invoice After Coinbase Withdrawal: Report

January 17, 2026
Jefferies’ Drops Bitcoin Over Quantum Computing Menace

Jefferies’ Drops Bitcoin Over Quantum Computing Menace

January 17, 2026
  • About
  • Privacy Poilicy
  • Disclaimer
  • Contact

© 2025- https://coininsight.co.uk/ - All Rights Reserved

No Result
View All Result
  • Home
  • Bitcoin
  • Ethereum
  • Regulation
  • Market
  • Blockchain
  • Ripple
  • Future of Crypto
  • Crypto Mining

© 2025- https://coininsight.co.uk/ - All Rights Reserved

Social Media Auto Publish Powered By : XYZScripts.com
Verified by MonsterInsights